PJM Is About to Bill 67 Million People for Data Centers That May Never Get Built

Eight state consumer offices want the December capacity auction postponed, and PJM's independent market monitor says data-center demand has already added $29.4 billion to the region's capacity costs.

A regional electric grid control room at night, with operators silhouetted in front of monitor banks

The consumer offices of Ohio, Delaware, West Virginia, Maryland, Pennsylvania and New Jersey, along with Illinois' Attorney General's Office and Citizens Utility Board, sent PJM's Board of Managers a letter on November 18 asking it to seek federal permission to postpone the capacity auction scheduled for December 9 through 15. That auction will set capacity prices for the 2029/2030 Delivery Year across a footprint that serves more than 67 million people. Proceeding now, the offices write, "risks the reliability of the region's grid and imposes billions of dollars in unnecessary capacity costs." They asked the board for a written answer by November 23.

The request lands on a tight calendar. PJM's own large-load materials put the posting of planning parameters on November 19 and the opening of the auction on December 9. Moving that date requires federal approval, and the last auction cleared at the maximum price the regulator allows while still coming up short of the capacity the region needs.

The monitor's arithmetic

PJM's independent market monitor, Monitoring Analytics, made its position explicit in the November 12 third-quarter State of the Market report. It recommended PJM postpone the 2029/2030 auction until every forecast data-center megawatt is removed from the procurement, with data centers lacking bilateral generation contracts instead procured in a separate Reliability Backstop Auction. By the monitor's calculation, including data-center load in the PJM Capacity Market has already produced an irreversible increase of $29.4 billion in capacity costs.

The forward-looking warning is larger. Running the December auction on PJM's 2026 load forecast, the monitor wrote, would price load that has been canceled or is unlikely to reach projected demand levels, and could add another $5 billion to $10 billion in data-center-related costs for all customers.

Ceiling prices, and still short

The 2028/2029 auction that PJM reported on July 14 cleared at the FERC-approved cap of $325 per MW-day, 2.5 percent below the prior year's cap. Cleared supply multiplied by that price totals $16.4 billion, though PJM notes that figure is not the total cost to load, because customers hedged through self-supply or bilateral contracts do not pay the clearing price. The procurement still came up 6,831 MW short of PJM's reliability requirement, after a shortfall of about 6,500 MW the year before. PJM itself described those as the first auctions in its history in which the entire RTO fell short of the requirement.

The December auction runs under a wider collar. FERC approved a cap of $337.83 per MW-day and a floor of $181.91 for the 2029/2030 event. The reliability requirement has grown to 158,712 MW, up 2,699 MW, while forecast peak load rose 3.6 percent to 171,916 MW. Demand is higher, the ceiling is higher, and paying the maximum still does not guarantee the capacity arrives.

What customers have actually paid

The monitor's accounting of the first nine months of 2026 against the same period of 2025 shows the squeeze in one line: the total cost of wholesale power rose from $79.19 to $111.61 per MWh, a 40.9 percent increase. Capacity rose 81.1 percent, from $10.72 to $19.42 per MWh, and energy rose 46.3 percent, from $48.47 to $70.89. Absent data-center load and its impact on capacity costs, the monitor calculates, the 2026 total would have been $101.66 per MWh. The data-center-driven gap is $9.95 per MWh, or 9.8 percent, and that figure excludes any effect on energy or transmission costs.

The fight over who pays

The consumer offices anchor their case in the January 2026 Statement of Principles, endorsed by PJM and the governors of all thirteen states, which committed the operator to large-load forecasts that are "real and verified." They also point to FERC's October 9 rejection of PJM's Interim Resource Adequacy Service proposal, and to Exelon's November 3 complaint challenging the continued reasonableness of the three-year forward auction, with relief that would begin with the 2030/2031 Delivery Year. PJM's visible response so far is procedural: a registry for new large loads and a "bring your own new capacity" process that adjusts the auction's demand curve for loads that qualify.

That is where the dispute sits. The eight offices frame the December auction as a question of allocation: whose bill carries demand nobody can yet confirm is real. Sixty-seven million consumers sit on the other side of a bill now priced off forecasts the monitor says include load that may never materialize. The board owes them a written answer, and the auction clock is already running.